A closer look at some of the facades we have delivered: the scope, the challenge and how our own team got it done.

01

SOLIHULL ENERGY CENTRE

SOLIHULL ENERGY CENTRE

SOLIHULL ENERGY CENTRE

Client: Maple Facades

Scope: Eurobond panels, louvres, fins, perforated panels, flashings and coping.

Challenge

Restricted site access and tight logistics.

Solution

The right lifting equipment and planned delivery points for the MERLO.

Outcome

Delivered safely, on programme, with a high-quality finish.

02

SANDWELL COLLEGE

SANDWELL COLLEGE

SANDWELL COLLEGE

Client: Sage BEC

Scope: BTS rainscreen cladding, re-clad project.

Challenge

Getting all the old materials safely down the scaffold and off site, without leaving anything behind.

Solution

Planning each day around what can physically be stripped and removed from the scaffold, working as one team with the other trades and booking enough time on the hoist.

Outcome

Now finishing the last elevation with a brand-new BTS rainscreen system, within programme.

03

122 BATH ROAD, BRISTOL

122 BATH ROAD, BRISTOL

122 BATH ROAD, BRISTOL

Main contractor: Vieo

Scope: Standing seam cold roof and walls.

Challenge

We took over from a contractor who had not delivered on time.

Solution

Teamwork and planning ahead.

Outcome

400m² of roof in 2 weeks and 270m² of walls in under 7 days as a start.

04

THE MILLINERS

THE MILLINERS

THE MILLINERS

Client: Lancer Scott

Scope: Re-clad project.

Challenge

Several contractors had gone bust before us, and the subcontractors who started the job weren't up to the task or the quality.

Solution

However difficult it got, our team stayed on task and helped the client make decisions. Every week we planned the work, constantly checked materials so we were never short, and worked with the scaffold crew on when they could strike.

Outcome

Delivered, built a strong relationship with the main contractor and were awarded new projects.

05

ST PETER'S COLLEGE

ST PETER'S COLLEGE

ST PETER'S COLLEGE

Client: Sage BEC

Scope: NBK baguettes and rainscreen cladding.

Challenge

A city-centre site with very little space for materials. Every week we had to plan what could fit on site and, more importantly, what we could install to clear space for the next week's deliveries.

Solution

We ran the job like a military operation. A brand-new product, a quirky design and many different corners meant recording every detail so each area passed inspection and we could move on.

Outcome

Delivered to a perfect standard without issues: a state-of-the-art building in a brand-new product that matches the surrounding architecture.

06

UWE ENGINEERING BLOCK

UWE ENGINEERING BLOCK

UWE ENGINEERING BLOCK

Client: Sage BEC

Scope: CORTEN rainscreen and Eurobond panels.

Challenge

Heavy panels that had to be lifted by forklift and hooked onto pre-made rails, and CORTEN needs weathering to build up its patina.

Solution

With the scaffold crew we built A-frames to lay out the new panels, and sprayed them twice a day with salt water to build the patina before they were installed.

Outcome

Our first project built properly, nearly 7 years ago, and it still looks outstanding today.

07

ST JOHN’S SCHOOL, WANTAGE

ST JOHN’S SCHOOL, WANTAGE

ST JOHN’S SCHOOL, WANTAGE

Main contractor: Central Cladding Systems

Scope: Timber cladding on SPIDI MAX FixFast bracket and rail, Rockwool insulation and Siderise fire barriers.

Challenge

800m² of rainscreen in a short window.

Solution

Working around the weather and cutting timber to size on site.

Outcome

Delivered within programme, as promised.